Level-I Category
|
Level-II Category
|
Level-III Category
|
Specification/ defining criteria
|
National Industries Classification Code
|
Notes
|
1 Energy Saving
|
1.1.Industrial Energy Saving
|
1.1.1 Device/Facility Construction and Operation
|
1. For the industries with a national standard of energy consumption
allowance for unit product, energy consumption of the device/facility (except
coal-fired power generation) or the process
≤ The reference value in the national standard of energy consumption
allowance for unit product.
2. For coal-fired generator units: Ultra supercritical or supercritical
CHP generator units with a capacity of no less than 300MW; back pressure
heating units without a capacity limit.
3. For projects adopting special technology with high efficiency and low
consumption, for instance, the ultra-high voltage (UHV) grid: identified
according to the special technology directly;
4. For biomass and low heat value (LHV) fuel power generation projects:
identified according to the property of biomass and LHV fuel.
5. For high energy efficiency application projects, for instance, LED lighting
: identified according to the technology of application.
|
E-Construction-48 Civil Engineering
Construction
|
The reference value of energy consumption allowance for unit product
(process): should refer to the national
standard of energy consumption allowance in each industry, or National Guidance for Industrial Energy
Consumption (2014), Chapter 4, Energy Consumption for Product and Process in
Key Industries, Table 4. Energy Consumption for Main Product and Process in
Key Industries.
|
1.1.2 Energy-saving Technology Improvement
|
Renovation projects adopting the energy saving technology listed in the
Catalogue for Promoting the National Key Energy-saving Technology (2014,
Energy-saving part );
Renovation projects of centralized heating complying with policies of “developing
large capacity units and suppressing small ones”, and “equivalent capacity replacement”.
Energy-saving renovation project in industrial, transportation and communication
area.
The renovated device/facility/equipment should meet at least one of the
following conditions:
1. The energy consumption of the device/facility or the process ≤ the
reference value of energy consumption allowance for unit product in national
standards.
2. the energy-saving efficiency of the renovated
device/facility/equipment ≥ the average energy-saving efficiency/capability
of energy-saving applications in the industry/area
|
E Construction-48 Civil Engineering Construction -4840
Mining Engineering Construction or-49 Construction and Installation
|
For projects with existing national standard of energy savings measurement
and verification, the energy saving effect should be evaluated according to
the standards.
|
1.2 Sustainable Building
|
1.2.1
Newly-built Green Building
|
The Newly-built buildings should meet following standards:
1. Newly-built industrial buildings: no less than two-star of the Evaluation Standard for Green Industrial
Building (GB/T50878-2013)
2、Newly-built resident and public buildings:
No less than two-star of the Evaluation
Standard for Green Building (GB/T50378-2006).
|
E Construction -47 Housing Construction
|
|
1.2.2 Energy Saving
Technology Improvement on Existing Building
|
The energy saving building renovation project includes but not limited
to: energy saving renovation on building envelope, heat supply system, heating
and cooling system, lighting, hot water supply facility.
|
E Construction -49 Construction and Installation; -50 architectural ornament and others
|
|
1.3 Energy Management Center
|
1.3.1 Facility Construction and Operation
|
An integrated energy management system which saves energy systematically,
by using automation and information technology and centralized management, to
implement centralized flat monitoring and digital management to each process
of production, distribution and consumption in corporate energy system, and
improve and optimize the balance of energy.
Including the purchase and installation of hardware facility, as well as
the development and application of supporting software.
|
I Information transmission, software and information technology services -65 Software and information technology services
-6510 Software development and -6520 Information system integration service
|
The project construction should be comply with the Construction Requirements of Energy Control Center for Industrial
Enterprises
|
1.4 Urban and Rural Infrastructure
Construction with Energy Saving Efficiency
|
1.4.1 Facility Construction
|
Include but not limited to:
1. Urban underground pipeline corridor project;
2. Construction and renovation projects of
adjusting the underground pipeline layout, route and buried depth, according
to the situation of urban waterlogging and heat-island effect;
3. Construction and renovation projects of
adjusting the district heating and water supply dispatching, as well as
improving the pipeline standard of heat insulation and moisture resistance, according
to the change of temperature.
|
E Construction -48 Civil Engineering Construction -4819
Other road, tunnel and bridge engineering construction;
-485 Wiring and piping engineering construction
|
Reference: the State Council Office’s Guidance on
Promoting the Construction of Integrated Urban Underground Pipeline Corridor
(Document No. 【2015】61)
|
2 Pollution Prevention and Control
|
2.1 Pollution Prevention and Control
|
2.1.1 Facility Construction and Operation
|
The construction and operation of waste treatment facility includes but
not limited to:
Treatment of waste water, sludge in waste water treatment, air pollution,
municipal solid waste (MSW) (including hazardous waste and medical waste),
waste treatment of integrated governance, treatment facilities and final treatment
facilities (including construction and operation of pipelines, collection,
transfer and storage facilities)
|
D Production and
supply of electricity, thermal power, fuel gas and water -46 Production and
supply of water-4620 Treatment and
Reuse of sewage; 7340 Marine service; N Management
of water, environment and public utilities -77 Ecological protection and environmental governance
|
Meet national standards for corporates with service of pollution
governance facility.
The Basel Convention on the Control of
Transboundary Movements of Hazardous Wastes and Their Disposal should be
complied with where the waste transfer is applicable.
|
2.2 Environmental Restoration Project
|
2.2.1 Project Implementation
|
The environmental restoration project includes but not limited to:
Integrated improvement of the urban polluted water, mine land reclamation
and ecological restoration, remediation of soil pollution and etc.
|
N Management of
water, environment and public utilities -77 Ecological protection and
environmental governance
|
The Basel Convention on the Control of
Transboundary Movements of Hazardous Wastes and Their Disposal should be
complied with where the waste transfer is applicable.
|
2.3 Clean Utilization of Coal
|
2.3.1
Device/Facility Construction and Operation
|
Device/Facility construction and operation projects conducting coal washing and
processing, using coal by quality and classification, adopting technologies
easy for pollution treatment to replace the traditional use of coal.
|
B Mining-06 Coal mining and washing;
E Construction-48 Civil Engineering Construction -4840
Mining Engineering Construction;
C Manufacturing-25 Petroleum refining and coking, nuclear fuel processing
-2520 Coking; 33 Metal products -3311 Metal structure manufacturing
|
Only device/facility construction and operation projects complying with the Action Plan of Clean Utilization of Coal (2015-2020),
and Opinions on Regulating the Coal
Fuel Demonstration Work
|
3 Resource Conservation and Recycling
|
3.1 Water Saving and Unconventional Water Use
|
3.1.1 Facility Construction and Operation
|
Include but not limited to: transformation of industrial water saving
technology, agricultural water saving irrigation, transformation of urban pipeline
network for water supply, integrated use of water resource, unconventional
water use (including sea water desalination, treatment and reuse of brackish
water, recycling water, mine water), and the supporting facility construction
and operation of sponge city.
|
E-Construction-48 Civil Engineering
Construction;
D Production and
supply of electricity, thermal power, fuel gas and water -46 Production and
supply of water-4690
Other treatment, use and distribution of water;
N Management of
water, environment and public utilities -76 Management of water conservancy-7620 Management of water resource;-7630 Collection and distribution of natural water
|
To optimize the allocation of water resource, the project should benefit climate
change adaption.
|
3.2
Redevelopment and Integrated Utilization of Tailings and Associated Mine
|
3.2.1
Device/Facility Construction and Operation
|
Specific to the redevelopment of tailings and associated mine with a
purpose of resource efficiency improvement, development of geothermal power, reinjection
and integrated utilization
|
B Mining-06 Coal mining and washing;
-07 Oil and gas exploitation;
-08 Ferrous metals mining and dressing;
-09 Non-ferrous metals mining and dressing;
-10 Nonmetal minerals mining and dressing;
-12 Other mining
industry
|
Not include the thermal power plant and mineral water manufacturer taking
advantage of the geothermal resource and water resource
|
3.3 Recycling and Utilization of Industrial Solid Wastes, Exhaust Gas,
and Effluent
|
3.3.1
Device/Facility Construction and Operation
|
Specific to collection and resourcelization of industrial solid waste, exhaust
gas, and effluent.
|
B Mining-06 Coal mining and washing;
C Manufacuring-14 Food
manufacturing-146 Manufacturing of
condiment and fermented
products;
-17 Textile;
-19 Leather, fur,
feather and its products;
shoemaking industry
-22 Paper making and paper
products;
-25 Petroleum refining and coking, nuclear fuel processing;
-29 Rubber and
plastic products;
-30 Nonmetal mineral products
D Production and supply of electricity, thermal power, fuel gas and water-4411
Thermal power generation;
C Manufacturing-31 Ferrous
metal smelting and rolling; -32 Non-ferrous metal smelting and rolling;
-33 Metal products-3360
Metal surface treatment and heat treatment processing
|
Meet national standards for corporates with service of pollution
governance facility.
|
3.4 Recycling, Processing and Utilization of Renewable Resource
|
3.4.1 Facility Construction and Operation of Recycling, Sorting and Dismantling
System
|
Specific to the construction and operation of waste collection system for
metal and non-metal production and processing in industrial area; construction
and operation of recycling, sorting and dismantling system for “city minerals”
resource, for instance, scrap car, scrap electronics, waste plastics, waste
steel, waste non-ferrous metal and etc.
|
C Manufacturing-42 Integrated use of wasted resource
|
|
|
3.4.2 Processing Device/Facility Construction and Operation
|
Specific to the construction and operation of waste processing and reuse
system for metal and non-metal production and processing in industrial area;
construction and operation of processing and reuse system for “city minerals”
resource, for instance, scrap car, scrap electronics, waste plastics, waste
steel, waste non-ferrous metal and etc.
|
C Manufacturing-42 Integrated use of wasted resource
|
|
3.5 Remanufacturing
of Electromechanical Products
|
3.5.1
Device/Facility Construction and Operation
|
Specific to construction and operation of
remanufacturing device/facility for electromechanical products, for instance, auto
parts, engineering machines, and machine tools.
|
C Manufacturing-38 Automobile
manufacturing-3660 Auto parts manufacturing;
-34 General equipment
manufacturing;
-33 Metal products
|
|
3.6 Recycling and
Utilization of Biomass Resource
|
3.6.1
Device/Facility Construction and Operation
|
Specific to construction and operation of
resourcelization device/facility for biomass waste, like straw, forest waste,
and household waste. This includes but not limited to:
Production device/facility for non-grain liquid
biomass fuel, power generation and heating device/facility for agricultural
and forest biomass, production device/facility for biogas, resourcelization device/facility
for household waste.
|
N Management of
water, environment and public utilities-78 Management public utilities-7820
Management of environmental sanitation;
A Agriculture , forestry
, husbandry and fishery-05 Agriculture , forestry , husbandry and fishery
services-0519 Other agriculture services;
-0529 Other forestry
services;
-0530 Husbandry
services;
D Production and
supply of electricity, thermal power, fuel gas and water-44 Production and
supply of electricity and thermal power-4419 Other electricity production
|
|
4 Clean Transportation
|
4.1
Railway Transportation
|
4.1.1 Facility Construction and Operation
|
Specific to the construction and operation (including technical transformation
and upgrading) of railway lines and terminals, and special supply station and
substation.
|
E Construction-48 Civil engineering construction-481 Engineering
construction of railway, road, tunnel and bridge -4811 Railway engineering construction
and
G Transportation, warehousing and postal industry-53 Railway
transportation
|
|
4.2 Urban Rail
Transit
|
4.2.1 Facility Construction and Operation
|
Specific to the construction and operation of rail transit, including
urban underground and light rail.
|
E Construction-48 Civil engineering construction-481 Engineering
construction of railway, road, tunnel and bridge -4811 Railway engineering construction
and
4819 Other engineering construction of road, tunnel and bridge
G Transportation, warehousing and postal industry -54 Road transportation-5412
Urban rail transit。
|
|
4.3 Public Urban and Rural
Transportation
|
4.3.1 Vehicle Purchase
|
Specific to purchase of public vehicles, including bus and electric bus
for passengers.
|
G Transportation, warehousing and postal industry -54 Road transportation-5411
Electric passenger bus
|
|
4.3.2 Facility Construction and Operation
|
Specific to the construction and operation of stations, BRT lines, and
other supporting facilities in public transportation, as well as the lines maintenance.
|
G Transportation, warehousing and postal industry -54 Road transportation-5411
Electric passenger bus
|
|
4.4
Waterway Transportation
|
4.4.1 Vessel Purchase
|
Specific to the phase-out of old vessels, and purchase of standardized
inland-waterway vessels, and vessels transport on costal water and ocean
which fully meet the latest international guidance, agreements and
standards.
|
G Transportation, warehousing and postal industry -55 Waterway transportation
|
References:
Implementation Plan of Improving Industrial
Structure, Promoting Industrial Transformation and Upgrading for Shipping
Industry (2013-2015); Measurement for Subsidy Management of Inland Ship
Standardization;
Working Focus on Energy Saving and Emission
Reduction in Transportation Industry 2014;
International Convention for the Prevention of
Pollution From Ships (MARPOL73/78) where the ocean shipping is applicable.
|
4.4.2
Waterway Regulation
|
Specific to the high-quality inland waterway dredging projects
|
E Construction- 48
Civil engineering construction- 4823 engineering construction of port and
shipping facility
|
References:
Implementation Plan of Improving Industrial
Structure, Promoting Industrial Transformation and Upgrading for Shipping
Industry (2013-2015);
Working Focus on Energy Saving and Emission
Reduction in Transportation Industry 2014;
International
|
4.5 Clean Fuel
|
4.5.1
Device/Facility Construction and Operation
|
Specific to the device/facility construction and operation which meets
the fuel production requirements of GB V standard gasoline and GB IV standard
diesel, or the technical transformation projects on existing fuel production with
improved cleanness standards (the GB V standard gasoline and GB IV standard
diesel should be met after the transformation project)
|
C Manufacturing- 35
Special equipment manufacturing
-3521 Manufacturing
of special equipment for oil refining and chemical production
|
|
4.5.2 Manufacturing
of Auto Fuel Products
|
Specific to the fuel products which meet the fuel production requirements
of GB V standard gasoline and GB IV standard diesel; and production of clean
fuel additives, like antiknock and oxidizer.
|
C Manufacturing-25 Petroleum refining and coking, nuclear fuel processing
-2511 Crude processing and petroleum product manufacturing
|
|
4.6 New Energy Automobile
|
4.6.1 Parts and Whole Car Manufacturing
|
Specific to whole car manufacturing, including new energy car like
electric car, fuel-battery car and natural-gas car; motor manufacturing,
energy storing device manufacturing
and other parts manufacturing.
|
C Manufaturing-36 Automobile manufacturing; -38 Electrical machinery and equipment manufacturing -381 Motor Manufacturing;
-384 Battery manufacturing
|
|
4.6.2 Supporting Facility
Construction and Operation
|
Specific to construction and operation of charging and energy supply
facility for new energy car.
|
E Construction- 48
Civil engineering construction
|
|
4.7 Internet Application on Transportation
|
4.7.1 Facility Construction and Operation
|
Specific to hardware and software facility and system that improves the
capability and efficiency of transportation and logistics. The facility or
system should base on mobile communication terminal, telecommunication base
station, GPS, and internet technology, apply the Internet of Things and Big
Data, to achieve integrated management of resource with comprehensive information
communication and sharing. The service targets directly on logistics and
transportation facility.
The construction and operation includes:
logistics information service platform, smart storage system, smart
logistics distribution system, online integrated system of transportation
resource (vehicle and ship), transportation management, executive information
system, smart monitoring system
and etc.
|
G Transportation, warehousing and postal industry;
I Information transmission, software and information technology services
|
The Internet ticket booking system for vehicle, ship and flight is not
included;
Applications mainly based on internet technology like taxi booking
software.
|
5 Clean Energy
|
5.1 Wind Power Generation
|
5.1.1 Facility Construction and Operation
|
Specific to construction and operation of wind farm (including supporting
wind power monitoring system, wind power prediction system, integrated
control system of wind farm and etc.)
|
D Production and
supply of electricity, thermal power, fuel gas and water-44 Production and
supply of electricity and thermal power-4414 Wind power generation
|
|
5.2 Solar Photovoltaic (PV) Power Generation
|
5.2.1 Facility Construction and Operation
|
The solar PV power plant and high-temperature solar power plants
(excluding distributed solar PV power generation system) should meet
following requirements:
1. No less than15.5% of the photoelectric
conversion efficiency for poly-crystalline silicon cell module, no more than
2.5% of the decay rate for the module within one year after the project’
start-up; no more than 0.7% of the decay rate afterwards.
2. No less than16% of the photoelectric conversion efficiency for mono-crystalline
silicon cell module, no more than 3% of the decay rate for the module within
one year after the project’ start-up; no more than 0.7% of the decay rate
afterwards.
3. No less than 28% of the photoelectric conversion efficiency for high
concentration PV (HCPV) cell module, no more than 2% of the decay rate for
the module within one year after the project’ start-up; no more than 0.5% of
the decay rate afterwards; no more than 10% of the decay rate in whole
project lifetime.
4. No less than 8% of the photoelectric conversion efficiency for silicon
based film cell module; No less than 11% of the photoelectric conversion
efficiency for copper indium gallium selenide (CIGS) film cell module; No
less than 11% of the photoelectric conversion efficiency for cadmium telluride (CdTe) film cell module;
No less than 10% of the photoelectric conversion efficiency for other film cell module;
5. No more than 20% of the decay rate for polycrystalline silicon,
monocrystalline silicon and film cell module in whole project lifetime.
|
D Production and
supply of electricity, thermal power, fuel gas and water-44 Production and
supply of electricity and thermal power-4415 Solar power generation
|
|
5.3 Smart Grid and Energy Internet
|
5.3.1 Facility Construction and Operation/Upgrading
|
Specific to grid construction and operation or technical transformation
and upgrading projects, which improve the balance and responsiveness of supply and demand, promote
integrated energy efficiency of the grid, lower the transformation of power
loss in transmission, and enhance the capability of renewables access.
1. Smart grid:
Grid construction and operation, as well as the technical transformation
and upgrading projects, which adopt smart electric equipment, integrated simultaneous
two-way information system and other advanced technologies.
2. Energy internet
construction and operation of grid, micro-grid and other energy (like natural
gas) internet, which integratedly applies power electronics, information and smart
management technology,connecting distributed energy (including
distributed renewable energy), distributed energy storage device and various
types of load, to achieve two-way energy flow and peer exchange and sharing.
|
D Production and
supply of electricity, thermal power, fuel gas and water-44 Electricity production-4420
Electricity supply; -45 Production and supply of fuel gas
|
|
5.4 Distributed Energy Resource
|
5.4.1 Facility Construction and Operation
|
Specific to construction and operation of energy management system, for
instance, regional energy station (including regional natural gas station), distributed
power generation like distributed photovoltaic power generation, distributed
energy access and peak-valley load regulating system, distributed power
trading platform, and etc.
|
D Production and
supply of electricity, thermal power, fuel gas and water-44 Production and
supply of electricity and thermal power-4420 Electricity supply
|
|
5.5 Solar Thermal Application
|
5.5.1
Device/Facility Construction and Operation
|
Specific to construction and operation of device/facility using solar
energy, which includes but not limited to:
Installation and operation of solar water heater; solar heating system; medium-high temperature solar heat
collection system; solar cooling system, heat pump air-condition system; solar
energy and air source heat pump hot water system, high-temperature megawatt
solar power generation device/facility.
|
D Production and
supply of electricity, thermal power, fuel gas and water-44 Production and
supply of electricity and thermal power
|
|
5.6 Hydropower Generation
|
5.6.1 Facility Construction and Operation
|
Specific to hydropower construction and operation like reservoir dam, hydraulic
tunnel, powerhouse, generator unit and etc.
|
D
Production and supply of electricity, thermal power, fuel gas and water-44 Production
and supply of electricity and thermal power- Hydropower generation
|
Meet requirements of Opinion of
Energy Work 2014 and other related documents, also the ecologic and
environmental protection and resettlement action plan of the project should
be assessed and approved
|
5.7 Other New Energy
Application
|
5.7.1 Facility Construction and Operation
|
Specific to engineering construction and operation of renewable energy
generation like geothermal power and marine power.
|
D Production and
supply of electricity, thermal power, fuel gas and water-44 Production and
supply of electricity and thermal power-4419 Other electricity production
|
|
6 Ecological Protection and Climate Change Adaption
|
6.1 Natural Ecological Protection and Protective Development of Tourism Resource
|
6.1.1 Facility Construction and Operation
|
Specific to natural reserve engineering; ecological restoration and vegetation conservation engineering; and
ecological protective development of tourism resource. These include but not
limited to:
National park, national geological park, the
protection project of natural heritage, construction and maintenance of national
and provincial natural reserve; construction and maintenance of ecological
function area, like specific wildlife habitat, wetland, desert, and prairie; coastal ecological restoration and vegetation conservation engineering; environmental pressure release on ecologically
vulnerable area (like ecomigration); urban gardening; land reclamation.
|
N Management of
water, environment and public utilities -77 Ecological protection and environmental governance-771 Ecological
protection; -78 Management public utilities-785 Management of parks and
scenic spots-7852 Management of scenic spot
|
|
6.2
Ecological Agriculture, Husbandry and Fishery
|
6.2.1 Project Implementation and Facility Construction
and Operation
|
Include integrating breeding project of agricultural, husbandry, and fishery
thoroughbred, manufacturing agricultural, husbandry, and fishery organic
products (including facility construction and operation). The output and
products of projects should meet following requirements or policies:
1. GB/T19630 standard of Chinese organic products;
2. Environment and quality standards of Agriculture Department, 7 general
guidance of pesticides, fertilizer, veterinary drug, feed and feed additives,
food additives, and animal hygiene, 45 product quality standards, product
mark should be in compliance with the “Measures of Mark Management for Green
Food”.
|
A Agriculture , forestry
, husbandry and fishery-01 Agriculture; -03 Husbandry; -04 Fishery
|
1. Projects should be in compliance with the Safety Management Regulation
of Agricultural Genetically Modified Organisms (GMOs);
2. Tobacco cultivation projects are excluded, as well as the fishing
methods which are harmful to marine ecological environment and diversity, for
instance, fish net fishing and large ocean drift net fishing;
3. Projects should be in compliance with the Rotterdam Convention on the
Prior Informed Consent Procedure for Certain Hazardous Chemicals and
Pesticides in International Trade where applicable; the production should be
in compliance with the Montreal Protocol on Substances that Deplete the Ozone
Layer.
|
6.3 Forestry Development
|
6.3.1 Project Implementation and Facility Construction
and Operation
|
Specific to the forest tending management and sustainable forestry
development project, including but not limited to:
1. Afforestation;
2. Forestry seed breeding and seedling production;
3. Underwood planting and underwood breeding.
|
A Agriculture , forestry
, husbandry and fishery-02 Forestry
|
1. Any species development
and (international) trade of animal and plats listed outside the Convention on International Trade in
Endangered Species of Wild Fauna and Flora(CITES);
2. Exclude
the natural commercial deforestation of
natural forest.
|
6.4 Emergency Prevention and Control of Disaster
|
6.4.1 Facility Construction and Operation
|
Specific to disaster monitoring, warning and emergency response system,
major river dyke construction and riverway dredging engineering, and other
engineering construction and operation including soil and water loss control,
ecological protection of forests and prairies and etc. These include but not
limited to :
1. Disaster monitoring of major infrastructure (water conservancy, transportation,
communication, electricity transmission, municipal infrastructure an etc.)
and emergency response system ;
2. Dyke construction
of major rivers, riverway dredging、flood storage area
engineering and maintenance, controlling hinge construction of main and tributary stream;
3. Construction and operation of hygiene emergency response for addressing
natural disaster and extreme weather, the production and storage of hygiene
emergency response facilities;
4. Monitoring, prevention and control system of forest fire, harmful and exotic
species;
5. Waning, prevention and control system of agriculture disaster; monitoring, prevention and control system
of animal epidemics;
6. Monitoring system
of marine disaster, ecological protection of prairie, control of soil and
water loss;
7. Natural forest
protection project (NEPP), converting cultivated land into forests,
construction and maintenance of shelter forest;
8. Production,
storage and transmission of disaster preparedness supplies.
|
I Information transmission, software and information technology services -65 Software and information technology services;
N Management of
water, environment and public utilities -76 Management of water conservancy- 7610 Management of flood control facilities;- 77 Ecological protection and environmental governance-771 Ecological
protection;
-78 Management public
utilities-7810 Management of municipal
facilities;
A Agriculture ,
forestry, husbandry and fishery-05 Agriculture , forestry, husbandry and
fishery services
|
|